Pipes are laid in trenches in the ground. It is most practical to lay the excavated ground alongside the trench. The following steps are a summary of the basic pipe installation procedure:
-
Position the coil alongside the trench

- Remove the packaging
- Place the end of the pipe in position
- Cut the outermost straps
- Roll the pipe alongside or straight into the trench
- Cut the middle straps
- Roll out further
- Cut the innermost straps
- Roll out completely
- Apply the dust caps or shrink caps
- Connect your pipes with couplings
- Conduct the pressure test – fill in the report
- Fill the trench with a first layer
- Apply the warning tape
- Fill up the trench.
The following guidelines should be followed during pipe installation:
-
Lay the pipes in a bed of sand

- Avoid damaging the casing, remove sharp objects from the ground
- Always grasp the transport pipe and not the outer tube
- Keep to the stated bending radii
- Lay the pipe with a slight curve bending from one side of the trench to the other
- Sketch how and where the pipe network runs on a plan, which you should keep.